Citizen's
Advisory Task Force Meeting 3
April 20, 2003
Meeting Minutes
DATE:
April 27, 2004
DATE
OF MEETING: April 20, 2004
LOCATION
OF MEETING: Bow Municipal Building
10 Grandview Road, Bow, NH
ATTENDED
BY:
Name
|
Affiliation
|
| Philip
Hastings |
City
of Concord |
| Tom
Raffio |
Concord
Chamber of Commerce |
| Bill
McConagle |
City
Council, City of Concord |
| Nan
Hagen |
Main
Street Concord |
| Eric
Anderson |
Selectman,
Town of Bow |
| Brian
Tufts |
Selectman,
Town of Pembroke |
| Pat
Sherman |
Concord
2020 |
| Howard
Moffett |
Concord
2020 |
| Richard
Heath |
Concord
Chamber of Commerce |
| Don
Lyford |
NHDOT |
| Ansel
Sanborn |
NHDOT |
| Bill
Hauser |
NHDOT |
| Subramanian
Sharma |
NHDOT |
| Gene
McCarthy |
McFarland-Johnson |
MEETING
MINUTES:
The Agenda for the meeting is attached and the meeting generally followed the
Agenda. These minutes are formatted to follow the Agenda Items.
1.0 Introductions
Eric Anderson opened the meeting and asked that all present
give their names and the organizations/group which they
represent.
2.0 Approval of Meeting No. 2 Minutes
The minutes from Meeting No. 2 were approved as submitted.
A request was made to add the project website address to
the minutes.
3.0 Project Update/Schedule
Don Lyford began by stating that the recent work on the
project focused on the completion of the Base Year 2000
Model and beginning the process of defining a project problem
statement. Ansel continued by stating the initial attempt
to write a purpose and need statement for the project was
met with confusion. The new process for the project will
first develop a problem statement that will lead to a purpose
and need statement. The goal for this project is to identify
all major issues in the planning phase so that they will
not have to be re-visited in the next phase.
Ansel
mentioned that the City of Concord is currently working
on their
Opportunity Corridor Project. That effort
will develop alternatives before this project does and
the hope is that this project can benefit from their work.
The NHDOT has and will continue to meet with the City’s
consultant (Cecil Group) to remain aware of their activities.
Ansel then described the schedule for the upcoming months.
The hope is that the brainstorming of ideas that will occur
up to the summer can be further developed by the team over
the summer. In the fall the committees can then begin to
evaluate and screen the alternatives to determine which
should be considered and which should not.
Ansel
concluded by mentioning that there has been some confusion
in Concord
concerning the direction of all of
the planning efforts. The new plan is to have broader public
meetings where one study is the focus, but where all of
the studies have a role. The meetings would have a presentation,
but also booths where each study could have information.
The first meeting should happen around June 8 with the
Opportunity Corridor being the focus and I-93 having a
role. Ansel also mentioned how we would like to replicate
this concept in Bow and Pembroke. Discussions have taken
place with Kerrie Diers to set up similar events in Bow
and Pembroke. In Bow the main event could be the current
study for Exit 1 and include the Route 3A Study, Bow’s
Master Plan and this study. For Pembroke the main event
could be Pembroke Hill Road and include Pembroke’s
Master Plan and this study. The committee members felt
that this was a good approach to reach the public.
4.0 Transportation Model
Gene began by stating that the work on the model has been
delayed. The land use data for the Year 2000 developed
by the state and by the City of Concord for their Master
Plan is slightly different. The sub-committee working on
land use is currently working on a compromise to resolve
the differences. Once the land use numbers are agreed upon
the Year 2000 model can be re-run and finalized.
Gene
distributed several graphs of traffic count data for
the I-93 corridor.
The graphs represent the highest
200 hours of traffic on the section of I-93 between Exist
12 and 13 for 2003. There was a graph for the total and
one each for southbound and northbound. On each graph the
30th highest hour was indicated. Gene mentioned that this
graph was created to address comments at previous meetings
pertaining to the appropriateness of the 30th highest hour
being used for the design hour. Each of the graphs indicates
that the 30th highest hour is on the “typical slope” of
the graph. The graphs show the special event or peak weekend
periods falling in the top 10 to 15 hours. Gene stated
that this indicates that the 30th highest hour is an appropriate
design hour period for the study.
Tom Raffio asked whether the current volume on I-93 indicates
a problem. Is the roadway at capacity? Gene responded that
the maximum capacity of a freeway lane is 2,200 vehicle
per hour per lane. This equates to a capacity of 4,400
vehicles per hour in each direction. Gene continued by
stating that the roadway is therefore at capacity for 30th
highest hour in 2000.
Several committee members asked for information that explains
the connection between capacity and level of service. Gene
stated that this would be done when the final model volumes
are complete.
5.0 TRC Land Use Sub-Committee
Gene explained that the Technical Review Committee has
formed a sub-committee to address the land use for the
model. The sub-committee has members from RPC who worked
on the Bow and Pembroke Master Plans, City of Concord,
RSG, NHDOT and others. The intent is to incorporate growth
patterns established in the master plans into the model.
This will ensure that the design year model will have the
most current planning information for land use. S. Sharma
added that an economic consultant is part of the team and
his responsibility will be to evaluate the impact an alternative
would have on land use and housing growth.
6.0 Planning Phase Overview
Gene began by stating this agenda item is to discuss the
Proposed Approach for Planning Phase memo dated March 19,
2004. This memo was developed to outline a new approach
for this project. Bill Hauser explained that the approach
described in the memo is different from the traditional
approach to project development. In the past, an environmental
document would be prepared for a project that had been
programmed in the ten-year plan , the purpose for which
may or may not have been clearly identified. When it came
time to measure the alternatives against the purpose and
need it became confusing.
Bill continued by stating that for this project the planning
is starting earlier so that we can understand the purpose
and need of the project before alternatives are developed.
The idea is to understand the problems that exist on I-93
and the opportunities that may also exist. The hope is
that community desires can be included in the project.
Bill did state that there would be no wish list of items,
but that the project should be aware of community desires
and try to incorporate them as much as is possible.
Bill next stated that screening criteria would be determined
so that alternatives can be measured. The reasons why an
alternative made it to the next phase or was eliminated
will be based upon how they measure up to the screening
criteria. This committee and the TRC will jointly determine
the criteria.
Bill McGonagle asked if this approach has been tried in
other places and whether examples of screening criteria
are available. Bill Hauser said that it has been done and
that examples are available. Gene stated that these examples
would be posted on the project website prior to the next
meeting.
Bill
McGonagle mentioned a statement from the memo that reads “eliminate alternatives… are inconsistent
with agency plans”. Bill McGonagle said that there
is a belief in the community that the NHDOT has a plan
for I-93 because it is programmed in the ten-year plan
and that this planning process is for show. Tom Raffio
asked what has been planned for the corridor. Ansel explained
that the project was once known as the “Bow -Concord
I-93 Widening Project” and is now known as simply
the “Bow- Concord Project”. The ten-year plan
has about $104 million programmed for this project even
though we don’t know what the project is. The ten-year
plan requires money to be programmed for design, land acquisition
and construction for all projects. Ansel believes that
the $104 million was an estimate developed as a placeholder
based upon some improvements to the corridor.
Ansel explained that the NHDOT is trying to work on a
plan to phase construction in a way to provide relief state-wide
without having to be controlled by funding that occurs
at a specific time. Gene stated that there is no pre-determined
alternative for the project.
7.0 Identification of Problems
Gene stated that this is the first step in the project
development process as described in the memo. The intent
is to collect input on the problems people currently have
with the corridor. This was begun by creating project displays
that were presented at several recent public events. At
these events the public was encouraged to submit written
comments or to place orange dots on the project map. A
map was shown that included all the orange dots placed
at the public meetings. Gene described some of the areas
where many dots were placed. These areas include Exit 1
on I-89, the connection to Route 106, the weaves at Exits14
and 15, and some others.
Gene then asked the committee members for their personal
opinion on the problems as well as those heard from their
constituents. Below is a list of the issues mentioned.