Citizen's
Advisory Task Force Meeting 1
September 17, 2003
Meeting Minutes
DATE:
September 25, 2003
DATE
OF MEETING: September 17, 2003
LOCATION
OF MEETING: New Hampshire Department of Transportation
John O. Morton Building
1 Hazen Drive, Concord, NH
ATTENDED
BY:
Name
|
Affiliation
|
| Philip
Hastings |
City
of Concord |
| Bill
McConagle |
City
Council, City of Concord |
| Jim
Bouley |
City
Council, City of Concord |
| Eric
Anderson |
Selectman,
Town of Bow |
| Steve
Buckley |
CNHRPC |
| Brian
Tufts |
Selectman,
Town of Pembroke |
| Pat
Sherman |
Concord
2020 |
| Richard
Heath |
Greater
Concord Chamber |
| Roger
Hawk |
City
of Concord, CDD |
| Don
Lyford |
NHDOT |
| Ansel
Sanborn |
NHDOT |
| Mark
Hemmerlein |
NHDOT |
| Subramanian
Sharma |
NHDOT |
| Rick
Woidt |
McFarland-Johnson |
| Jed
Merrow |
McFarland-Johnson |
| Gene
McCarthy |
McFarland-Johnson |
| Steve
Lawe |
Resource
System Group |
MEETING
MINUTES:
The Agenda for the meeting is attached and the meeting generally followed the
Agenda. These minutes are formatted to follow the Agenda Items.
1.0 Introductions/Committee Overview
Don Lyford of the NHDOT brought the meeting to order and asked that all present
give their names and the organizations/group for which they represent.
Don then discussed the committees that have been assembled for the project
and distributed a list of the members of each committee. He then distributed
the guidelines for the CATF that describes the role of this committee along
with its authority. Copies of these two documents are included with these minutes.
2.0 Selection of CATF Chairperson
Don mentioned that a chairperson is needed. It was decided at the end of the
meeting to wait until the next meeting to elect a chairperson. Don mentioned
that this committee does not necessarily need a vice-chairperson and that a
secretary would not be needed.
3.0 Project Overview and History
Don outlined the major steps of the project. This project is currently in Part
A where a reasonable range of alternatives must be determined and a Purpose
and Need developed. Part A is scheduled to run through the Fall of 2004. Part
B would then continue the study of alternatives and prepare an environmental
document culminating with a project necessity and a Public Hearing. The Public
Hearing should be in 2007. Final design would then begin with construction
beginning in 2010.
Don then discussed the history of the Bow-Concord Study. The first Study was
concluded in 1992 where extensive highway improvements were proposed. The results
of this study were not well received by the surrounding communities. The Concord
2020 efforts also studied I-93 and made some recommendations for the vision
of I-93 in Concord. Some of the recommendations from The Concord 2020 report
will be studied further in this project. Finally, the reconstruction of Exit
13 was completed with the understanding that I-93 could be widened in the future.
Exit 13 will accommodate three lanes in each direction.
4.0 Project Development Process
Ansel Sanborn of the NHDOT made a presentation on the Project Development Process
to be undertaken on this project He stated that the Bow-Concord project is
currently on the Planning Step.
Ansel then presented two concepts for the process. The first is the ?NEPA Driven
Process? which is the process as defined in the NEPA law. This is the traditional
way projects have been done. He then presented the ?Community Driven Process?
where there is much more public input at the early stages of a project. This
is also referred to as ?Context Sensitive Solutions?. The hope is that the
proposed transportation solution fits with the overall context/vision that
the community has for itself. Fortunately, the three surrounding communities
to the project, Concord, Bow and Pembroke, are all in the midst of their master
plan updates. The vision input necessary for this project is the same as that
needed for the master plans. The ultimate goal is for the solution to be jointly
developed between the NHDOT and the stakeholders to ensure a project that is
successful from all perspectives.
Pat Sherman commented that the Bow-Concord Project presents a special opportunity
because the NHDOT is serious about working with communities.
5.0 Study Methodology
Rick Woidt of McFarland-Johnson (M-J) began by presenting the consultant team
that will conduct the study
Rick described the limits of the project and the constraints of the study.
Exit 13 is a constraint, as is the limitation of I-93 to a maximum of six lanes.
Rick then described a list of Transportation Considerations for the study.
Many of these were concepts that came from the Concord 2020 study while others
are concepts being considered by other stakeholders.
Gene McCarthy of M-J then presented the Engineering/System Planning scope of
the project. He stated that the work to date has been mostly data collection,
base plan preparation and modeling.
Steve Lawe of Resource Systems Group (RSG) then gave an in depth presentation
on the scope of the transportation modeling for the project. Steve discussed
the model being used, the model process, model operation, and how the model
will be used for the Bow-Concord Project. The main points concerning the model
are that it has been enhanced to be a person based model not vehicle based
so that it can model mode choice. Also, the model contains updated population
data from the 2000 census and employment data from the state.
Steve used an example to illustrate what can be expected from the model. Eric
Anderson asked if the model could assess the impact of tolls. Steve stated
that the model can because it assesses incentives and disincentives such as
time and cost.
Bill McGonagle asked if the model can assess the change in housing demand in
the region if an improved infrastructure allows people to commute a longer
distance. Steve explained that the model will show the transportation effects
on a proposed land use scenario. He also explained that our team includes Russ
Thibeault of Applied Economic Research (AER) who will perform a qualitative
analysis of the impact of a proposed alternative on land use and development.
The main points stressed concerning the design year model are that employment,
land use and transportation infrastructure for the design year 2030 need to
be assumed before the model can be completed. It will be important that all
participants work towards reaching a consensus on these future assumptions.
Pat Sherman asked how the traffic information would be explained to the public.
It was discussed that numbers and tables would be used but that visual simulations
could also be used with aerial photographs to give a real life feel to the
traffic.
Gene continued with a discussion of the traffic analyses that would be conducted
for the existing and proposed roadways. He stated that RSG would provide volumes
that would be analyzed and described by a Level of Service (LOS). The LOS is
a simple letter designation A to F that depicts the driving conditions of the
roadway.
Jed Merrow of M-J next presented the environmental scope of the project. Jed
stated that one of the differences in this project is that the evaluation of
environmental impacts or benefits is being considered earlier in the process.
Traditionally the environmental effects would be assessed after the development
of alternatives. For the Bow-Concord Project the intent is to evaluate the
environmental consequences during the development of alternatives, so that
alternatives that have excessive environmental impact and no chance of being
permitted can be ruled out early on. Jed also mentioned that the resource agencies
are being involved earlier in the project.
Jed went on to describe the process of collecting the data in two ways where
certain resources would be evaluated on a broader scale to determine the effect
on the context of the resource. Other resources would be evaluated on the direct
impact to them by an alternative.
Jed finished his presentation by stating he hopes to view this project more
by the potential benefits and enhancements to the environment rather than the
impacts. He believes the opportunities include improving access to the Merrimack
River, improving recreation trail connectivity, enhancing aesthetics, and preserving
riparian habitat.
Pat Sherman asked about archaeological investigations. Jed explained that Victoria
Bunker is on our team to perform archaeological investigations and Liz Hengen
is on our team for historic investigations.
Gene McCarthy completed this discussion by describing the Completion of Phase
A. Phase A will develop a Purpose and Need Statement and a Reasonable Range
of Alternatives that will be described in a Summary/Classification Report.
6.0 Public Participation Process
Rick Woidt began the Public Participation discussion by describing the tasks
that M-J currently has in its scope. These include public meetings, a newsletter,
a website and a project design center. The project design center is envisioned
to be a mobile station that can be set up at different venues or events to
present the project to the public.
Bill McGonagle asked how the other communities would become involved with the
process. Rick stated that the hope is that the CNHRPC would take the lead on
this coordination. Steve Buckley later stated that his experience working on
the CNHRPC is that it is extremely difficult getting the other communities
involved. He stated that the outlying communities do not actively participate
in the current process for nominating projects through the Transportation Advisory
Committee. The hope is that this project, which may propose widening I-93,
will create interest.
Ansel Sanborn next described the collaborative process that is planned for
this project. The hope is to get the public interested in this project early
enough to avoid surprises at the last minute. The plan is to include the Bow-Concord
Project in other transportation public presentations. The plan with the City
of Concord is to have this project as one piece of a large public meeting that
presents the master plan, opportunity corridor and other city projects. The
hope is that the public will be more inclined to show up if they know they
can get all the information they need at one meeting and not have to show up
for multiple meetings. The hope is also to use this approach in Bow and Pembroke.
Ansel presented slides that the City's consultant prepared that outline their
approach and schedule. The first meeting of their Master Plan Coordinating
Committee is October 9 with a public Community Forum on November 15.
7.0 Proposed Project Schedule
Rick presented the proposed schedule that shows project completion in Fall
2004.
8.0 Discussion
Pat Sherman asked about the scope of the transit component of the project.
Rick explained that TranSystems is on our team and their role is to advise
on providing an adequate corridor to preserve the rail corridor through Concord.
9.0 Public Comments/Input
There were none.
10.0 Next CATF Meeting
No date or time was set. It was decided that the meeting should occur before
the planned public meeting on November 15. It was decided to have members respond
to an e-mail message as to times they could attend.
Submitted by,
Gene McCarthy, P.E.
McFarland-Johnson, Inc.