Technical
Review Committee Meeting No.1
November
21, 2003
MEETING
MINUTES
DATE: December
8, 2003
DATE
OF MEETING: November 21, 2003
LOCATION
OF MEETING: Community Resource Center
Commercial Street, Concord, NH
ATTENDED
BY:
Name |
Affiliation
|
| Don
Lyford |
NHDOT |
| Ansel
Sanborn |
NHDOT |
| Bill
Hauser |
NHDOT |
| Mark
Hemmerlein |
NHDOT |
| Subramanian
Sharma |
NHDOT |
| John
Butler |
NHDOT |
| Roger
Hawk |
City
of Concord, CDD |
| Bill
Klubben |
Town
of Bow Planning |
| Kerrie
Diers |
Town
of Pembroke Planning |
| Mike
Tardiff |
CNHRPC |
| Nick
Alexander |
CNHRPC |
| Bill
O’Donnell |
FHWA |
| Dick
Lemieux |
FHWA |
| Gino
Infascelli |
NHDES |
| Bill
Ingham |
NHFGD |
| Mickey
McIver |
Concord
Area Transit |
| George
Thayer |
Guilford
Rail |
| Jed
Merrow |
McFarland-Johnson |
| Gene
McCarthy |
McFarland-Johnson |
| Chris
Bowler |
McFarland-Johnson |
| Steve
Lawe |
Resource
System Group |
MEETING
MINUTES:
The
Agenda for the meeting is attached and the meeting generally
followed the Agenda. These minutes are formatted to follow
the Agenda Items.
1.0
Introductions/Committee Overview
Don
Lyford of the NHDOT brought the meeting to order and
asked that all present give their names and the organizations/group
for which they represent.
The
name of the committee was discussed first. Is this a
review or advisory committee? The conclusion was that
the name would remain the Technical Review Committee
(TRC) but that the role of the committee will go beyond
review. The hope is that the TRC will:
· advise
the study team
· review Purpose and Need
· develop alternatives
· review alternatives
· collect information/data
Mike
Tardiff of Central New Hampshire Regional Planning Commission
(CNHRPC) mentioned that he hopes the TRC can help obtain
data that will be necessary for the development of the
transportation model. Gene McCarthy of McFarland-Johnson
(M-J) agreed with this and added that the TRC members
can be extremely helpful in obtaining information resulting
from the on-going updates to the master plans of Concord,
Bow and Pembroke.
2.0
Project Overview/Status
Gene
McCarthy gave an overview of the project including the
project limits. He emphasized that this is a study of
the transportation needs of the I-93 corridor from south
of I-89 to just north of I-393. He added that other regional
transportation concepts that are being considered would
be evaluated in the study to determine their affect on
I-93. Some of the ideas include a connection to Route
106, Exit 16 1/2 on I-93 and Exit 2 1/2 on I-393, which
come out of Concord 2020. Concepts for I-93 developed
during Concord 2020 will also be evaluated. These include
providing better access to the Merrimack River, potentially
lowering I-93 near Exit 14, improving the aesthetic of
the corridor, and preserving the rail corridor through
Concord. An interchange south of I-89 on I-93 will also
be evaluated. These are concepts that are being discussed
by the community that are not currently funded or programmed.
Gene
stated that efforts to date have been to collect data,
develop base maps and begin the transportation modeling.
The Citizens Advisory Task Force (CATF) has also met
twice.
3.0
Project Objectives
The
discussion focused on the two main objectives for Phase
A of the study, developing a Purpose and Need statement
and developing a range of reasonable alternatives.
Gene
stated that the CATF will begin looking at the Purpose
and Need at its next meeting. A draft will be prepared
listing potential needs. Examples of other Purpose and
Need statements will be made available. The TRC is also
expected to help develop the Purpose and Need. The Purpose
and Need will be challenging because the I-93 corridor
serves many purposes including local trips, commute trips
and regional vacation trips.
The
development of alternatives should also begin soon. Gene
stated that the CATF would begin brainstorming ideas
at its next meeting. The evaluation of alternatives will
not be done until the design year model is developed.
See Section 4.0 for a discussion of the model and its
schedule.
Gene
stated that the alternatives are meant to be for the
I-93 corridor only. The model will be developed with
assumed configurations for other improvements within
the region. A discussion ensued about potential improvements
outside of I-93. Bill O’Donnell of FHWA mentioned
that there could be a “package of improvements” designed
to achieve the project goals that may not necessarily
include improvements to I-93. The extent of an alternative
will therefore be determined by its ability to meet the
project Purpose and Need.
4.0
Project Scope
Gene
began by stating that Phase A of the study has several
key tasks, they include:
· transportation
modeling
· alternatives development
· environmental studies
· public participation
4.1
Transportation Model
The
study will use a base model year of 2000 because the
census of 2000 provides excellent data to build the model.
The base model is near completion. The design year for
the project is 2030. The design year model is yet to
begin.
Steve
Lawe of RSG continued the discussion by asking when the
land use will be ready for the 2030 model. The plan has
been to incorporate land use plans from each of the new
master plans and incorporate these into the model. Steve
said that RSP could make assumptions on the land use
but these would certainly be different than those to
be developed in the master plans. Roger Hawk stated that
the Concord Masterplan would not have information ready
until the spring at the earliest. Ansel mentioned that
the latest TIP shows this project being delayed. The
consensus was that the project should wait for the three
master plans to develop their land use and then incorporate
this information into the 2030 model.
4.2
Alternatives Development
The
Exit 14/15 area was discussed. Desires to provide access
to the Merrimack River, preserve the rail corridor, lower
I-93 and improve operations of the ramps were discussed.
Roger
Hawk of the City of Concord gave an overview of the Opportunity
Corridor Study the City has just begun. This is a master
plan study of the corridor bounded by Exit 12 and Exit
15 and by Main Street and the river. Much of this area
is the old rail yard.
4.3
Environmental Studies
Jed
Merrow of M-J explained that Phase A will do more environmental
studies than would normally be done. The reason for this
is to identify critical impacts that would remove an
alternative from consideration. He stated that mostly
existing data and information would be used.
4.4
Public Participation Program
Gene
McCarthy discussed the various elements of the program
including the various committees, meetings, newsletters
and the website. He also mentioned the project design
center. This is a mobile presentation that could be taken
to local events and used to inform the public about the
project. Bill Klubben of the Town of Bow suggested the
Town Meeting Day in Bow. He said that this is the biggest
public event of the year and it occurs in March.
The
committee made several other recommendations for informing
the public. Placing an ad in the local newspapers, i.e.
Bow Times. Having the project newsletter as a newspaper
insert or supplement. The idea of using the primary season
was mentioned.
5.0 Proposed Project Schedule
A
project schedule was distributed to all committee members.
However, the dates for the modeling, traffic analysis
and alternatives evaluation will need to be revised.
The design year model will be delayed until Spring 2004,
the alternative model runs will be delayed until Summer
2004, the traffic analysis will be delayed until Fall
2004 with a final report by the end of 2004.
Bill
O'Donnell asked about the content and purpose of the
Summary/Classification Report. Is it meant to be a Scoping
Report? Bill Hauser
responded by saying that the Summary/ Classification
Report is more of a rationale report and that a formal
Scoping Report may come later. He added that the report
would also recommend the level of NEPA document that
will be required for the project.
6.0
Discussion
What
if the study determines that improvements other than
to I-93 can satisfy the Purpose and Need? The consensus
was that the study should look at all aspects of transportation
and evaluate them on their ability to meet the Purpose
and Need. Improvements to local roads, expansion of rail,
expansion of bike paths or trials, or operational improvement
only to I-93 can be evaluated. It may be necessary to
re-evaluate the scope of the project if the alternatives
recommended to be brought forward include other improvements
or new roadways. This includes the Route 106 Connector.
If the connector proves to reduce the demand on I-93
it may be necessary to re-scope the project.
It
was mentioned that the scope of the study limits the
widening of I-93 to 6 lanes. This limitation reflects
the recommendation from Concord 2020. Roger Hawk stated
that if the traffic numbers indicate 6 lanes are not
sufficient, the City would be willing to re-evaluate
their position.
The
idea of have reversible lanes was mentioned. During the
two race weekends during the year, lanes on I-93 are
reversed to get additional capacity in the peak direction.
Could this be done on a permanent basis to get peak capacity
without building as may lanes?
Are
alignment shifts under consideration? Could the sharp
horizontal curve between I-89 and Exit 12 be improved?
It was re-emphasized that all improvements should be
discussed and a determination made as to whether they
should be rejected or carried forward.
The
concept of using the 30th highest traffic volume hour
was questioned. Is this an appropriated measure of the
use of I-93? The 30th hour falls on a Friday in July
when recreation traffic is at its peak. Should we look
at other peaks to see how the volumes compare? Gene McCarthy
suggested preparing a graph of the highest hours of the
year. This may help determine if the 30th highest is
appropriate for the study.
7.0
Next TRC Meeting
The
next meeting was tentatively scheduled for December 17.
The hope is that some of the resource agencies that were
not able to make this meeting would be able to make the
December 17 date. The meeting would present much of the
same material as this one with the hope of getting their
input as soon as possible.
Subsequent
to the meeting it was determined that not enough of the
other agencies could make the December 17. Therefore,
the next TRC meeting has been re-scheduled for January
21, 2004 at 2:00 p.m. The location for the meeting has
yet to be determined.
Submitted
by,
Gene McCarthy, P.E.
McFarland-Johnson, Inc.